BP Did Not Use Riserless Drilling at Macondo

BP Development of Riserless Drilling

Following severe and expensive drilling problems experienced by BP in 2003 at the West Azeri template in the South Caspian, a decision was taken to develop a system of riserless drilling in order to avoid such problems in the future. The company AGR Subsea developed a Tophole Drilling Package names Riserless Mud recovery System [RMR] which enables drilling the tophole section using weighted inhibited drilling mud, leading to improved hole stability, reduced wash outs, improved well control both with regard to shallow gas and shallow water flows [SWF].

A field trial was conducted in December 2004 following the establishment of a Joint Industry Project [JIP] was established funded by the Norwegian Research Council, Statoil-Hydro and AGR in order to qualify the RMR technology for use in up to 450 m water depths.

The RMR system was used on 15 wells at the BP West Azeri problem site (see previous) and in Deepwater Gunashli and Shah Deniz in the South Caspian. By mid-2007,  28 wells had been drilled on BP projects in the South Caspian using this technique, as well as at Sakhalin offshore Russia, specifically to avoid potential problems related to geohazards. By 2007, Shell E&P and the BP America Production Company had joined the original Demo 2000 JIP, with the specific aim to “develop, manufacture and perform a field trial of an RMR system for use in 5000 ft. of water depth in the GOM”.

Subsequently a large-scale field trial was conducted from a deepwater semisubmersible offshore Sabah, Malaysia, in September 2008. A joint industry group comprising AGR Subsea, BP America, Shell and the Norwegian Research DEMO 2000 [the original RMR JIP] program and supported by Petronas undertook this work. This group set out to advance subsea mud return technology from its established commercial market of shallow-water applications, 1,800 ft (549 m) or less, to deepwater depths and drilling requirements. Novel equipment and deployment methods were designed, developed, delivered, tested and proven to a demanding schedule.

The shallow water (< 450 m) version of RMR has been used commercially since 2003 on more than 100 wells worldwide. Statoil was the first operator in the GoM to adopt the RMR system, which has been used on the Discoverer Americas drill ship on the Statoil-operated Krakatoa prospect. The RMR system allows the circulation of mud, reducing the total consumption and discharges to sea to a quarter of the amount compared with conventional methods. The cost of mud and the transportation to the drill ship are significantly reduced and technology allows deeper drilling depths for shallow casing strings, again reducing the overall drilling time per well. Minimising the number of casing strings in deepwater drilling where you may run out of options.

Statoil currently has two drilling units in operation in the Gulf of Mexico. RMR technology has successfully been used by Statoil on the Norwegian Continental Shelf in 19 operations over the past years. As a partner with BP in the South Caspian and with BP America a partner in the successful development of the RMR technique, the question must be asked as to why it has not been adopted in the GoM by BP in general and at Macondo specifically, in view of the known severe potential geohazard related drilling problems that might be encountered at location, specifically related to shallow water flows , a weak unstable formation and gas hydrates, all common to the South Caspian.

 If the RMR system was not considered to be available or suitable for use at Macondo, for whatever reason, when it was used extensively by BP in the South Caspian and at Sakhalin then it is arguable that the Macondo well should not have been drilled where and when it was, using the outdated riskier conventional technique of cementing casing strings with a long riser. Could it be that BP in Houston were not fully aware of the RMR developments or rejected its use on cost grounds or as an “unknown step-out for the GoM”? BP are generally not as innovative as Statoil.

Advertisements

About thegallowglaich

Offshore Engineer and Researcher
This entry was posted in Uncategorized. Bookmark the permalink.

One Response to BP Did Not Use Riserless Drilling at Macondo

  1. Wayne Needoba says:

    Re your comment “Could it be that BP in Houston were not fully aware of the RMR developments or rejected its use on cost grounds or as an “unknown step-out for the GoM”? BP are generally not as innovative as Statoil” There is not doubt BP could have rejected the use of RMR but how would the use of it impact the design of the 9 5/8″ x 7″ long string of casing? Note that I had the fluke of observing some Statoil decision making and certainly the do try to avoid complexity and standards by selling out assets at a convenient time and leave abandonment to a national oil company.

    From what I can see, both regulator and operator in the industry are under manned and are winging the decision making process where there is complexity. Certainly on a team by team basis there is competency but there isn’t the transparency to the public or competence in the regulatory to determine competence in a complex situation.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s